Batane Reservoir Scheme

Project

Financial Details

Physical Progress/Status

Statutory Status

Present Financial Source for Execution

Target Year of Completion

Starting Year

1976

River

Batane

Basin

 

CCA

1.406 Th.Ha. (Jharkhand)

10.72 Th.Ha. (Bihar)

Potential Envisaged

9.87 Th.Ha.

Potential Created Till 03/11

7.38Th.Ha

District benefited

Aurangabad, Gaya

 

Original Estimated Cost

4.01 Cr. (1975)

Latest Estimated Cost

116.02 Cr

AA

33.12 Cr. (439/ 19.03.96)

AA

63.00 Cr. (2534/ 11.11.2006)

Exp. till 03/2011

75.92 Cr.

 

Dam and Barrage

100% (spillway gate to be installed by Jharkhand)

Left main canal Completed

 

Right main canal

Jharkhand (0 to 14.14) - 0%
Bihar (14.14 to 31.46) - 100%

Bottleneck

Inter-state problem with Jharkhand and Land Acquisition for distributories in Bihar

Forest Land involved

 Nil

Environ. and forest clearance

Not required.

 

Formerly-
Under AIBP

At Present-
Under State Plan (Vide Notification No.-यो०मो०-4 (AIBP) 04/28/2013-396 dated 03/07/13)

2014